My finished deck project, took about four weeks for demo and rebuild.
Demolition took 3 days, concrete took about 4 days altogether. We mixed and poured by hand due to it being around one yard total.
Framing took about 2 weeks, and decking took almost a week, railings took about 3 days.
I’m including the clients review of the job, as well.
Thanks for looking!
Deck prices start at $25/sq foot for Cedar and $30/sq ft for composite,
Goes up from there depending on if it’s ground level, difficult terrain, or a number of other things.
The handrails used on this cedar deck were very comparable price and labor wise to Cedar railings,
We used cedar 4x4s, 2x4s and powder coated aluminum spindles.